milyon88 ACEN set to replace coal plant with $1.5-B solar facility
Updated:2024-12-03 04:05    Views:195

Ayala-backed ACEN Corp. is keeping its aggressive renewable buildup with a planned $1.5-billion investment targeted to finance a massive solar farm and energy storage system.milyon88

According to ACEN senior vice president and head of corporate communications and sustainability Irene Maranan, the midmerit integrated renewables and energy storage system (Iress) would replace the 246-megawatt (MW) South Luzon Thermal Energy Corp. (SLTEC) coal plant in Batangas, which the group hopes to shut down by 2030.

“We’re looking at $1.5 billion as capex (capital expenditures) for the Iress,” she told the Inquirer on the sidelines of Hybrid Energy: Bridging the Transition to Renewables last Friday.

Article continues after this advertisement

A portion of the budget would come from revenues to be generated from selling transition credits. Additional funds are expected from its partnership with investment firm Temasek and Singapore’s Keppel Ltd.

FEATURED STORIES BUSINESS BIZ BUZZ: The crackdown on digital banking ‘backdoor’ BUSINESS ACEN set to replace coal plant with $1.5-B solar facility BUSINESS The uncomfortable truth: Why your business won’t hit its 2025 targets

Transition credits are a financing approach used to fund the phaseout of coal plant assets while pursuing replacement facilities that use renewable energy. ACEN earlier teamed up with the Rockefeller Foundation and Monetary Authority of Singapore to pilot the use of transition credits.

Maranan said the Iress would feature a 1,400-megawatt peak (MWp) solar plant to be integrated with a 1,600 megawatt-hour (MWh) battery energy storage system.

Article continues after this advertisement ‘Reliable’ power

She said the planned development was “oversized” and meant to provide “reliable and dispatchable power” to meet the grid’s needs.

Article continues after this advertisement

“The foregone coal plant output is matched 100 percent. The impact on the grid is negligible given that the renewables’ intermittency is mitigated by the energy storage system,” the official said in her speech.

Article continues after this advertisement

Since the group wants to retire the SLTEC by 2030—10 years earlier than scheduled—the executive said construction works for Iress must start by 2027 or 2028.

Building the project, she noted, may take three to four years.

Article continues after this advertisement

“Before 2030, we should be able to have about one phase or two phase[s] ready, completed and already supplying to the grid,” she said.

ACEN, however, has yet to decide on the location of the project.

Maranan also said ACEN has been in close coordination with the Department of Energy for the Iress plan, but noted it has yet to secure a notice to proceed from the agency.

Your subscription could not be saved. Please try again. Your subscription has been successful.

Subscribe to our daily newsletter

SIGN ME UP

By providing an email address. I agree to the Terms of Use and acknowledge that I have read the Privacy Policy.

Currentlymilyon88, ACEN has expanded its renewable capacity to 6.8 gigawatts (GW). It hopes to scale this up to 20 GW by 2030. INQ

READ NEXT My life in public service Recent storms to increase cost of producing palay EDITORS' PICK 20,000 more foreign Pogo workers to leave PH as deadline nears - BI (G)I-DLE confirms full-unit contract renewal at Melon Music Awards 2024  Colmenares: ICC may be preparing for Duterte trial Dolly de Leon wins Best Supporting Actress at Critics Choice AAPI event Dismissed Cebu City Mayor Mike Rama holds presscon at city hall NBC misidentifies Lea Salonga during Macy’s Thanksgiving Day parade MOST READ Comelec junks House bid of 'manghihilot’ from Laguna Solons understand Marcos’ advice vs VP Duterte's impeachment First impeachment complaint vs VP Sara filed at House De Lima: Fund misuse, threats among grounds for impeaching VP Duterte Follow @FMangosingINQ on Twitter --> View comments

上一篇:tmt play BIZ BUZZ: The crackdown on digital banking ‘backdoor’
下一篇:vvjl The uncomfortable truth: Why your business won’t hit its 2025 targets

Powered by MOJILI-MOJILI Casino-MOJILI OFFICIAL HOMEPAGE @2013-2022 RSS地图 HTML地图